HOME »
India’s Commitment »
India’s Country Programme
Status of ODS Phaseout in India
CFC Production Sector Phaseout in India
Accelerated Phaseout of CFCs
HCFC Phaseout Management Plan
Halon Production Sector Phaseout in India
Foam Manufacturing Sector Phaseout Project
Commercial Refrigeration Sector (Manufacturing) Phaseout Plan
National CFC Consumption Phaseout Plan (NCCoPP)
National CTC Phaseout Plan
Strategy for Solvent to phase-out ODS in SMEs in India
Aerosol Sector
HPMP SERVICING SECTOR
HCFC PHASE-OUT MANAGEMENT PLAN STAGE-I SERVICING SECTOR
Activities under the HPMP in the Servicing Sector
HPMP Technicians Training Programme Calendar 2013 - 14
TRAINING PROVIDERS AND BROCHURE



India’s Country Programme

The Executive Committee, at its 32nd meeting, adopted a strategic framework for the MLF in view of the compliance period started with effect from 2001. Accordingly, Article 5 Countries were advised to revise the Country Programme and to prepare the national strategies for complying with provisions of the Montreal Protocol obligations.

 

The UNDP is the Implementing Agency and assisted in preparing Country Programme Update.

 

A draft Country Programme Update has been prepared based on the following information: -

 

  • Country Programme – 1993
  • Article 7 data and sectoral data under Country Programme Progress Report
  • Implementation of individual and group projects approved by the Executive Committee during 1993-2000
  • Terminal project in foam, aerosol, commercial refrigeration.
  • National CFC Consumption Phase-out Plan (NCCoPP).
  • National CFC Production Phase-out Plan
  • National CTC Production and Consumption Phase-out Plan
  • Ozone Depleting Substances (Regulation and Control) Rules, 2000 and its amendments
  • Information provided by a few states

A National Stakeholders’ Workshop to discuss the draft Country Programme Update was convened on 30th and 31st January 2006 in New Delhi. The major stakeholders invited for this workshop were line Ministries of the Government of India and Industries associations. Besides, the members of Technology and Finance Standing Committee (TFSC) and Empowered Steering Committee (ESC), local representatives of Implementing Agencies were also invited.

 

Over the past twelve years since the approval of India’s original Country Programme for Phase-out of Ozone Depleting Substances in 1993, India made significant progress in controlling the production and consumption of ODS. From a consumption level of 10,370 MT of ODS in 1991, the unconstrained demand was forecasted at about 96,000 MT by 2005. The consumption of these substances by end-2004 was only about 9,000 MT annually. These reductions were achieved with technical and financial assistance from the Multilateral Fund and implementing agencies and due to proactive policy actions by Government of India. The following table summarizes the ODS phase-out activities, both completed and ongoing, in various sectors:

 

Table-19: Summary of ODS Phase-out Activities in All Sectors

 

Sector

Number of Projects

Funding (US$)

Phase-out (ODP MT)

Aerosols Sector

27

3,227,739

689

Foams Sector

159

34,785,641

4,373

Firefighting Sector

18

2,458,701

2,162

Refrigeration & Air Conditioning Sector

49

32,254,823

3,203

Solvents Sector

41

61,358,042

12,966

Production Sector (including Halons)

2

84,600,000

22,988

Total

296

218,684,946

46,381

 

Of the above-mentioned activities, over 70% of the activities in terms of ODS phase-out are now completed. Almost all of the individually approved projects have been completed. The implementation of performance-based sector and national-level phase-out plans in the Foams, Refrigeration & Air Conditioning and Solvents sectors is well on course, with the respective annual phase-out targets met or exceeded.

 

To Download, Click Here, [ CP Update Handbook ]



Feedback | Related Links | Announcements | Events | Newsletters | Photo Archive | What's New | Site Map | Site Search | Disclaimer
Best viewed on screen resolution of 1024 x 768
Copyright @2008 Ozonecell.com, All Rights Reserved.

Visitor No: 263431
[Last updated on 27 Jun 2017]